Contents

1                      Introduction                                                                          

1.1                   Purpose of the Manual                                                    

1.2                   Project Description                                                           

1.3                   Objective of the EM&A                                                       

1.4                   Scope of the EM&A Programme                                    

1.5                   Organisation & Structure of the EM&A                   

1.6                   Arrangement for Advanced Works and River Modification Works Contract                                                                                  

1.7                   Structure of the EM&A Manual                                   

2                      EM&A General Requirements                                         

2.1                   Introduction                                                                          

2.2                   Construction Phase EM&A                                              

2.3                   Operation Phase EM&A                                                      

3                      Air Quality                                                                                

3.1                   Introduction                                                                          

3.2                   Monitoring Parameters                                                   

3.3                   Monitoring Location                                                          

3.4                   Monitoring Equipment                                                       

3.5                   Monitoring Frequency                                                      

3.6                   Environmental Compliance and EAP                          

4                      NOISE                                                                                           

4.1                   Introduction                                                                          

4.2                   Methodology and Criteria                                             

4.3                   Monitoring Equipment                                                       

4.4                   Monitoring Locations                                                        

4.5                   Baseline Monitoring                                                           

4.6                   Impact Monitoring                                                               

4.7                   Environmental Quality Performance Limits          

4.8                   Event and Action Plan                                                       

4.9                   Audit Requirements                                                            

5                      Water Quality                                                                        

5.1                   Introduction                                                                          

5.2                   Construction and Operational Phases                   

6                      Ecology                                                                                    

6.1                   Introduction                                                                          

6.2                   Construction Phase                                                           

6.3                   Post-Construction Phase                                               

7                      Waste Management                                                             

7.1                   Introduction                                                                           

7.2                   Waste Management Practices                                      

7.3                   Waste Management EM&A                                                

7.4                   Mitigation Measures                                                           

8                      Cultural Heritage                                                              

8.1                   Introduction                                                                          

8.2                   Archaeology                                                                         

8.3                   Built Heritage                                                                        

9                      Landscape & visual                                                             

9.1                   Introduction                                                                          

9.2                   Construction Phase                                                           

9.3                   Post - Construction Phase                                             

10                    Environmental Site Inspection                                      

10.1                 Site Inspections                                                                     

10.2                 Compliance with Legal & Contractual Requirements    

10.3                 Environmental Complaints                                            

10.4                 Log-Book                                                                                  

11                    Reporting                                                                                 

11.1                 General                                                                                    

11.2                 Baseline Monitoring Report                                          

11.3                 Monthly EM&A Reports                                                     

11.4                 Quarterly EM&A Summary Reports                            

11.5                 Annual/ Final EM&A Review Reports                           

11.6                 Data Keeping                                                                           

11.7                 Electronic Reporting of EM&A Information          

11.8                 Interim Notifications of Environmental Quality Limit Exceedances     

 

Annexes

 

Annex A       Implementation Schedule

Annex B       Data Record Sheet for TSP Monitoring

Annex C       Construction Phase Noise Monitoring Data Record Sheet

Annex D       Compliant Log

 

 

1                                            Introduction

1.1                                      Purpose of the Manual

Changjiang Water Resources Protection Institute (CWRPI 長江水資源保護科學研究所) in association with ERM-Hong Kong Ltd was jointly commissioned by the Shenzhen River Regulation Office of the Shenzhen Municipal Government (深圳市治理深圳河辦公室) and the Drainage Services Department (DSD) of the HKSAR Government to undertake an Environmental Impact Assessment (EIA) Study for the Regulation of Shenzhen River Stage 4 (hereafter referred to as the Project).  This Environmental Monitoring and Audit (EM&A) Manual (hereafter referred to as the Manual) is a supplementary document to the EIA Report.

The Manual has been prepared in accordance with the EIA Study Brief (No. ESB - 200/2008) and the Technical Memorandum of the Environmental Impact Assessment Process (EIAO-TM).  The purpose of the Manual is to provide information, guidance and instruction to personnel charged with environmental duties and those responsible for undertaking EM&A work during construction and operation of the Project.  It provides systematic procedures for monitoring and auditing the environmental performance of the Project.

This Manual contains the following information:

·           Responsibilities of the Contractor(s), Environmental Team (ET), and the Independent Environmental Checker (IEC) with respect to the EM&A requirements during the implementation of the Project;

·           Project organisation;

·           Requirements with respect to the construction and operational programme schedule and the necessary EM&A programme to track the varying environmental impact;

·           Details of the methodologies to be adopted including field, laboratory and analytical procedures, and details on quality assurance and quality control (QA/QC) programme;

·           Preliminary definition of Action and Limit (A/L) levels;

·           Establishment of Event and Action plans (EAPs);

·           Requirements for reviewing pollution sources and working procedures required in the event of exceedances of applicable environmental criteria and/or receipt of complaints;

·           Requirements for presentation of EM&A data and appropriate reporting procedures; and

·           Requirements for review of EIA predictions and the effectiveness of the mitigation measures and the EM&A programme.

An ET shall be appointed to conduct the monitoring works and to provide specialist advice on the undertaking and implementation of environmental responsibilities.  The ET will be led and managed by the ET Leader.  The ET Leader will have relevant education, training, knowledge, experience and professional qualifications and the appointment will be subject to the approval of the Director of Environmental Protection.  Suitably qualified staff will be included in the ET, and ET should not be in any way an associated body of the Contractor(s).  For the purpose of this manual, the ET Leader, who will be responsible for, and in charge of, the ET, is referred to as the person delegated the role of executing the EM&A requirements for the Project.

To maintain strict control of the EM&A process, an IEC will be engaged to verify and validate/ audit the environmental performance of the Contractor(s).  Sufficient and suitably qualified professional and technical staff will be employed by the IEC, as required under the EM&A programme for the duration of the Project.

1.2                                      Project Description

1.2.1                                Project Scope

The location and alignment of the Project components are shown in Figure 1.1 to 1.6.  The scope of the Project comprises:

·           Improvement of an approximately 4.5km long section of Shenzhen River;

·           Re-provision of the boundary patrol road and about 4.5km of boundary fence affected by the Project;

·           Dry weather flow interception of the sewage currently discharged from Shenzhen side into the Project area; and

·           Associated landscaping works.

1.2.2                                Construction Programme

The construction phase of the main works will last for 44 months.  An advanced works contract on the construction of boundary fence and boundary patrol road on Hong Kong side will be included as part of this Project and will last for about 36 months between the period of February 2012 and January 2015.  The proposed construction programme is presented in Table 1.1.

Table 1.1        Construction Programme

 

Phase

Date

Duration

Works Description

1

Advanced Works

February 2012 to January 2015

36 months

Construction of boundary fence and boundary patrol road on HK side

2

Preparation Phase

March to July 2013

5 months

Tendering; land resumption

3

Pre-construction

August to September 2013

2 months

Construction of site access roads and site office, site clearance, site preparation works etc.

4

Construction

October 2013 to December 2016

39 months

Main construction works of the Project such as dredging of river sediment and soil excavation, construction of flood retardation pond, boundary fence and boundary patrol road on Shenzhen side, river modification works, dry weather flow interception works etc.

5

Post-construction

January 2017 to March 2017

3 months

Demolition of temporary structures, landscaping works etc.

 

1.2.3                                Construction Works

Temporary river diversion will be carried out, if necessary, before the commencement of the construction of the river regulation works.  The main construction works include boundary patrol road and boundary fence, temporary river diversion, soil excavation, embankment construction, sewage diversion works and landscaping works.

1.3                                      Objective of the EM&A

The broad objective of this EM&A Manual is to define the procedures of the EM&A programme for monitoring the environmental performance of the Project during design, construction and operation.  The construction and operational impacts arising from the implementation of the Project are described in the EIA Report.  The EIA Report also specifies mitigation measures and good construction practices that will be needed to comply with the environmental criteria or further minimise the potential impacts.  These mitigation measures and their implementation requirements are presented in the Implementation Schedule of Mitigation Measures (see Annex A).

The main objectives of the EM&A programme are to:

·           provide a database of environmental parameters against which to determine any short term or long term environmental impacts;

·           provide an early indication should any of the environmental control measures or practices fail to achieve the acceptable standards;

·           confirm that the mitigation measures recommended in the EIA Report are properly incorporated into the design of the Project;

·           confirm that the design complies with the recommendations of EIA Report and the conditions of Environmental Permit (EP);

·           clarify and identify potential sources of pollution, impact and nuisance arising from the works for the responsible parties;

·           confirm compliance with regulatory requirements, contract specifications and EIA study recommendations;

·           monitor performance of the mitigation measures and to assess their effectiveness;

·           take remedial actions if unexpected issues or unacceptable impacts arise;

·           verify the environmental impacts predicted in the EIA; and

·           audit environmental performance.

The EIA Study indicates that an EM&A programme will only be required for the construction and post-construction phases of this Project.  Unacceptable environmental impacts are not predicted to occur during the operation phase, an EM&A programme for the operation phase is not considered necessary.  A summary of the requirements for each of the environmental parameters is detailed in Table 1.2.

Table 1.2        Summary of EM&A Requirements

Parameter

Phases

Construction

Post – Construction

Operation

Air Quality

M (a) + SI

-

-

Noise

M (a) + SI

-

-

Water Quality

M (a) + SI

-

-

Waste

SI (b)

-

-

Terrestrial Ecology

SI (b)

-

M

Fisheries

-

-

-

Landscape and Visual

SI (b)

SI (b)

-

Land Contamination

-

-

-

Cultural Heritage

(c)

-

-

Notes:

(a)   M – Environmental monitoring for the River Modification and Associated Works

(b) SI -  Site inspection for both River Modification and Associated Works and Advanced Works

(c)   The Project Proponent should inform AMO immediately in case of discovery of archaeological deposits in the course of excavation works. No monitoring or site inspection is required for archaeology & built heritage.  

1.4                                      Scope of the EM&A Programme

The scope of this EM&A programme is to:

·           establish baseline dust and noise levels at specified locations and implement monitoring requirements for dust and noise monitoring programme during construction;

·           implement inspection and audit requirements for water quality, waste management and landscape and visual impacts;

·           liaise with, and provide environmental advice (as requested or when otherwise necessary) to construction site staff on the significance and implications of the environmental monitoring data;

·           identify and resolve environmental issues and other functions as they may arise from the works;

·           check and quantify the Contractor(s)’s overall environmental performance, implementation of EAPs, and remedial actions taken to mitigate adverse environmental effects as they may arise from the works;

·           conduct monthly reviews of monitored impact data as the basis for assessing compliance with the defined criteria and to verify that necessary mitigation measures are identified and implemented, and to undertake additional ad hoc monitoring and auditing as required by special circumstances;

·           evaluate and interpret environmental monitoring data to provide an early indication should any of the environmental control measures or practices fail to achieve the acceptable standards, and to verify the environmental impacts predicted in the EIA;

·           manage and liaise with other individuals or parties concerning other environmental issues deemed to be relevant to the construction process;

·           conduct regular site inspections and audits of a formal or informal nature to assess:

-            the level of the Contractor(s)’s general environmental awareness;

-            the Contractor(s)’s implementation of the recommendations in the EIA and their contractual obligations;

-            the Contractor(s)’s performance as measured by the EM&A;

-            the need for specific mitigation measures to be implemented or the continued usage of those previously agreed; and

-            to advise the site staff of any identified potential environmental issues;

·           produce monthly EM&A reports which summarise EM&A data, with full interpretation illustrating the acceptability or otherwise of any environmental impacts and identification or assessment of the implementation status of agreed mitigation measures.

1.5                                      Organisation & Structure of the EM&A

The EM&A will require the involvement of DSD, an ET, an IEC and the Contractor(s) (see Figure 1.7).  The roles and responsibilities of the various parties involved in the EM&A process are further expanded in the following section.

1.5.1                                Project Organisation

DSD will appoint an ET to conduct the site inspection and monitoring and, to provide specialist advice on implementation of environmental responsibilities.

The ET will have previous relevant experience with managing similarly sized EM&A programmes and the ET Leader will be a recognised environmental professional, with a minimum of seven years relevant experience in impact assessments and EM&A programmes.  The ET Leader will be responsible for, and in charge of, the ET; and will be the person responsible for executing the EM&A requirements, and to provide advice (if required) on environmental clauses for Contract Specifications of the Project.

To maintain strict control of the EM&A process, DSD will appoint an independent environmental consultant to act as the IEC to verify and validate/ audit the environmental performance of the Contractor(s) and works of the ET.  The IEC will have previous relevant experience with checking and auditing similarly sized EM&A programmes and the IEC will be a recognised environmental professional, with a minimum of seven years relevant experience in impact assessments and EM&A programmes.

Roles & Responsibilities

DSD will:

·           employ an ET to undertake monitoring, laboratory analysis and reporting of environmental monitoring data, and site inspection of construction works;

·           employ an IEC to audit and verify the overall environmental performance of the works and to assess the effectiveness of the ET in their duties;

·           supervise the Contractor(s)’ activities and confirm that the requirements in the Manual and the Contract Documents are fully complied with;

·           develop appropriate contract clauses to confirm that the Contractor(s) will have qualified professionals to interface with the DSD/ ET /IEC to fulfil the EIA/EP requirements;

·           inform the Contractor(s) when action is required to reduce impacts in accordance with the EAPs;

·           adhere to the procedures for carrying out complaint investigation; and

·           participate in joint site inspections undertaken by the ET and IEC.

The Contractor(s) will:

·           work within the scope of the construction contract and other regulatory requirements;

·           provide assistance to the ET in carrying out environmental monitoring and site inspections;

·           submit proposals on mitigation measures in case of exceedances of the A/L levels in accordance with the EAPs;

·           implement measures to reduce impact where A/L levels are exceeded;

·           implement the corrective actions instructed by DSD/ET/IEC;

·           participate in the site inspections undertaken by the ET and the IEC, as required, and undertake any corrective actions instructed by DSD/ETL/IEC; and

·           adhere to the procedures for carrying out complaint investigation.

The ET will:

·           monitor various environmental parameters as required in this Manual;

·           assess the EM&A data and review the success of the EM&A programme determining the adequacy of the mitigation measures implemented and the validity of the EIA predictions as well as identify any adverse environmental impacts before they arise;

·           carry out regular site inspection to investigate the Contractor(s)’s site practice, equipment and work methodologies with respect to pollution control and environmental mitigation, and effect proactive action to pre-empt issues;

·           review the Contractor(s)’s working programme and methodology, and comment as necessary;

·           review and prepare reports on the environmental monitoring data and site environmental conditions;

·           report on the environmental monitoring results and conditions to the IEC, Contractor(s), DSD and EPD;

·           recommend suitable mitigation measures to the Contractor(s) in the case of exceedance of A/L levels in accordance with the EAPs; and

·           adhere to the procedures for carrying out complaint investigation.

The IEC will:

·           review and audit the implementation of the EM&A programme and the overall level of environmental performance being achieved;

·           arrange and conduct monthly independent site audits of the works;

·           validate and confirm the accuracy of monitoring results, monitoring equipment, monitoring stations, monitoring procedures and locations of sensitive receivers;

·           audit the EIA recommendations and requirements against the status of implementation of environmental protection measures on site;

·           on an as needed basis, audit the Contractor(s)’s construction methodology and agree the appropriate, reduced impact alternative in consultation with DSD, the ET and the Contractor(s);

·           adhere to the procedures for carrying out complaint investigation;

·           review the effectiveness of environmental mitigation measures and project environmental performance including the proposed corrective measures;

·           review EM&A report submitted by the ET leader and feedback audit results to ET by signing off relevant EM&A proformas; and

·           report the findings of site audits and other environmental performance reviews to DSD, ET, EPD and the Contractor(s).

1.5.2                                Key Contact Information

Key contact information will be provided in a similar format as in Table 1.3.

Table 1.3        Contact Information - to be completed prior to commencement of construction

Name

Position

Telephone

Facsimile

E-mail

DSD – EP Holder

To be confirmed

 

 

 

 

Contractor(s)

To be confirmed

 

 

 

 

ET

To be confirmed

 

 

 

 

IEC

To be confirmed

 

 

 

 

1.6                                      Arrangement for Advanced Works and River Modification Works Contract

The Project construction will be undertaken by two separate contracts, one for the Advanced Works within the HKSAR and one for the River Modification Works within both the HKSAR and the Shenzhen Municipality.  The EM&A organisation and structure for both contracts shall be the same.  Environmental site audit is recommended for both contracts to ensure that the good construction site practices are implemented.

As the scale and nature of the Advanced Works is small and the EIA Report concluded that the construction of the Advanced Works will not cause adverse environmental impact, environmental monitoring is not required for the Advanced Works.  The environmental monitoring requirement for the River Modification Works is specified in Sections 3 and 4 of this Manual.

1.7                                      Structure of the EM&A Manual

The remainder of the Manual is set out as follows:

·           Section 2 sets out the EM&A general requirements;

·           Section 3 sets out the EM&A requirements for air quality;

·           Section 4 sets out the EM&A requirements for noise;

·           Section 5 sets out the audit requirements for water quality;

·           Section 6 sets out the audit requirements for terrestrial ecology;

·           Section 7 sets out the audit requirements for waste management;

·           Section 8 sets out the audit requirements for cultural heritage;

·           Section 9 sets out the audit requirements for landscape and visual;

·           Section 10 describes the scope and frequency of site environmental inspection; and

·           Section 11 details the reporting requirements for the EM&A programme.


2                                            EM&A General Requirements

2.1                                      Introduction

In this section, the general requirements of the EM&A programme for the Project are presented.  The scope of the programme is developed with reference to the findings and recommendations of the EIA Report.

2.2                                      Construction Phase EM&A

2.2.1                                General

Potential environmental impacts, which were identified during the EIA process and are associated with the construction phase of the Project, will be addressed through the monitoring and controls specified in this Manual and in the construction contracts.

During the construction phases of the Project, air quality, noise, water quality, ecology, landscape and visual and waste will be subject to EM&A, with environmental monitoring being undertaken for construction dust and noise as determined in the EIA.  Monitoring of the effectiveness of the mitigation measures will be achieved through the environmental monitoring programme as well as through site inspections.  The inspections will include within their scope, mechanisms to review and assess the Contractor(s)’s environmental performance, ensuring that the recommended mitigation measures have been properly implemented, and that the timely resolution of received complaints are managed and controlled in a manner consistent with the recommendations of the EIA Report.

2.2.2                                Environmental Monitoring

The environmental monitoring work throughout the Project period will be carried out in accordance with this EM&A and reported by the ET.  Monitoring works will cover construction dust and noise and will form an important part of the whole EM&A programme. 

2.2.3                                Action and Limit (A/L) Levels

A/L Levels are defined levels of impact recorded by the environmental monitoring activities which represent levels at which a prescribed response is required.  These Levels are quantitatively defined later in the relevant sections of this Manual and described in principle below:

·           Action Levels: levels beyond which there is a clear indication of a deteriorating environmental conditions for which appropriate remedial actions are likely to be necessary to prevent environmental quality from falling outside the Limit Levels, which would be unacceptable; and

·           Limit Levels: statutory and/or agreed contract limits stipulated in the relevant pollution control ordinances, Hong Kong Planning Standards and Guidelines (HKPSG) or Environmental Quality Objectives established by the EPD.  If these are exceeded, works will not proceed without appropriate remedial action, including a critical review of plant and working methods.

2.2.4                                Event and Action Plans (EAPs)

The purpose of the EAPs is to provide, in association with the monitoring and audit activities, procedures for ensuring that if any significant environmental incident occurs, the cause will be quickly identified and remediated.  This also applies to the exceedances of A/L limits identified in the EM&A programme.

2.2.5                                Site Inspections & Audits

In addition to construction dust and noise monitoring as a means of assessing the ongoing performance of the Contractor(s), the ET will undertake site inspections of on-site practices and procedures each month.  The primary objective of the inspection programme will be to assess the effectiveness of the environmental controls established by the Contractor(s) and the implementation of the environmental mitigation measures recommended in the EIA Report.  The IEC will undertake monthly site audits to assess the performance of the Contractor(s) and the effectiveness of the ET.

Whilst the inspection and audit programme will complement the monitoring activity, the criteria against which the inspection/ audits will be undertaken will be derived from the Clauses within the Contract Documents which seek to enforce the recommendations of the EIA Report and the Manual.

The findings of site inspections and audits will be made known to the Contractor(s) at the time of the inspection to enable the rapid resolution of identified non-conformities.  Non-conformities, and the corrective actions undertaken, will also be reported in the monthly EM&A Reports.

Section 10 of this Manual presents details of the scope and frequency of on-site inspections and defines the range of issues that the audit protocols will be designed to address.

2.2.6                                Enquiries, Complaint and Requests for Information

Enquiries, complaints and requests for information may occur from a wide range of individuals and organisations including members of the public, Government departments, the press and television media and community groups.

Enquiries, complaints and requests for information concerning the environmental effects of the construction works, irrespective of how they are received, will be reported to DSD and directed to the ET which will set up procedures for the handling, investigation and storage of such information.  The following steps will then be followed:

1)        The ET Leader will notify DSD of the nature of the enquiry.

2)        An investigation will be initiated to determine the validity of the complaint and to identify the source(s) of the issue.

3)        The Contractor(s) will undertake the following steps, as necessary:

·            investigate and identify source(s) of the issue;

·            if considered necessary by DSD following consultation with the IEC, undertake additional monitoring to verify the existence and severity of the alleged complaint;

·            liaise with EPD to identify remedial measures;

·            liaise with the IEC to identify remedial measures;

·            implement the agreed mitigation measures;

·            repeat the monitoring to verify effectiveness of mitigation measures; and

·            repeat review procedures to identify further practical areas of improvement if the repeat monitoring results continue to substantiate the complaint.

4)        The outcome of the investigation and the action taken will be documented on a complaint log (see Annex D).  A formal response to each complaint received will be prepared by the Contractor(s) within five working days and submitted to DSD, in order to notify the concerned person(s) that action(s) has been taken.

5)        Enquires which trigger this process will be reported in the monthly EM&A Reports which will include results of inspections undertaken by the Contractor(s), and details of the measures taken, and additional monitoring results (if deemed necessary).  It should be noted that the receipt of complaint or enquiry will not be, in itself, a sufficient reason to introduce additional mitigation measures.

The complainant will be notified of the findings, and audit procedures will be put in place to verify that the issue does not recur.

2.2.7                                Reporting

Baseline and impact monitoring, monthly, quarterly and final reports will be prepared by the ET on behalf of DSD and certified by the ET Leader and verified by the IEC.  The reports will be submitted to the Contractor(s), DSD and EPD.  The monthly EM&A Reports will be prepared and submitted within two weeks of the end of each calendar month.

2.2.8                                Cessation of EM&A

The cessation of EM&A programme is subject to the satisfactory completion of the Final EM&A Report, agreement with the IEC and approval from EPD.

2.3                                      Operation Phase EM&A

As no unacceptable impacts were identified during the operation phase of the Project, no EM&A programme is considered necessary for the operation phase.  However, should other operational licenses that require specific monitoring or audit conditions or practices be required, plans under the respective ordinances/ guidelines will need to be put in place.


3                                            Air Quality

3.1                                      Introduction

Environmental site audit is required for ensuring implementation of recommended dust control measures and monitoring of dust is required during the construction phase of the River Modification Works.  Since no adverse air quality and odour impacts are anticipated during the operation phase, no EM&A programme is required.

The general requirements, methodology, equipment, and mitigation measures for the monitoring and audit of potential construction phase air quality impact are described in the following sections.  The mitigation measures recommended to control air quality impacts are summarised in Annex A.

3.2                                      Monitoring Parameters

Monitoring of the Total Suspended Particulates (TSP) levels will be carried out by the ET to ensure that construction works will not cause adverse dust impacts to identified air sensitive receivers (ASRs).  Timely action shall be taken to rectify the situation if an exceedance is detected.  All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, any other special phenomena and work progress of the concerned site shall be recorded.  A sample data log sheet is shown in Annex B.

3.3                                      Monitoring Location

Two locations are proposed for construction dust monitoring as listed in Table 3.1.  The locations of the monitoring station are presented in Figure 3.1.

Table 3.1        Construction Dust Monitoring Stations

Monitoring Station

Description

Remarks

AM1

Ta Kwu Ling Village

During construction works at works areas III or IV

AM2

Tsung Yuen Ha

During construction works at works areas I or II

The status and locations of ASRs may change after issuing this Manual and the location of the proposed construction dust monitoring station may need to be adjusted accordingly.  If such changes occur, the ET shall propose an updated monitoring location for agreement by the Engineer Representative (ER) of DSD, Contractor(s), IEC and the EPD.

When alternative monitoring location is proposed, the following criteria, as far as practicable, shall be followed:

·           At the site boundary or such locations close to the major dust emission source;

·           Close to the sensitive receptors;

·           Take into account the prevailing meteorological conditions; and

·           For monitoring location located in the vicinity of the ASR, care shall be taken to cause minimal disturbance to the occupants during monitoring.

When positioning the high volume air sampler (HVS), the following points shall be noted:

·           a horizontal platform with appropriate support to secure the samples against gusty wind shall be provided;

·           no two samplers shall be placed less than 2m apart;

·           the distance between the HVS and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the HVS;

·           a minimum of 2m separation from walls, parapets and penthouses is required for HVS at the rooftop;

·           a minimum of 2m separation from any supporting structure, measures horizontally is required;

·           no furnace or incinerator flue is nearby;

·           airflow around the sampler is unrestricted;

·           the HVS is more than 20m from the dripline;

·           any wire fence and gate to protect the HVS, shall not cause any obstruction during monitoring;

·           permission must be obtained to set up the HVS and to obtain access to the monitoring stations; and

·           a secured supply of electricity is needed to operate the HVS.

3.4                                      Monitoring Equipment

Continuous 24-hour and 1-hour monitoring shall be performed using HVS with appropriate sampling inlets installed, located at the designated monitoring station.  The performance specification of HVS shall comply with the standard method “Determination of Suspended Particulate Matter in the Atmosphere (High Volume Method)” as stipulated in US EPA Standard Title 40, Code of Federation Regulations Chapter 1 (Part 50 Appendix B).

The HVS is fitted with a conditioned, pre-weighed filter paper, at a controlled rate.  After sampling for 1 hour or 24 hours, the filter paper with retained particles shall be collected and returned to the laboratory for the testing of TSP levels.  Continuous 1-hour and 24-hour TSP levels shall be calculated from the ratio of the mass of particulates retained on the filter paper to the total volume of air sampled.  The analysis process shall normally take about two days to complete.

HVS in compliance with the following specifications shall be used for carrying out 24-hour TSP monitoring:

·           0.6 - 1.7 m3 per minute (20 - 60 standard cubic feet per minute) adjustable flow range;

·           equipped with a timing/ control device with ± 5 minutes accuracy for 24 hours operation;

·           installed with elapsed-time meter with ± 2 minutes accuracy for 24 hours operation;

·           capable of providing a minimum exposed area of 406 cm2 (63 in2);

·           flow control accuracy: ± 2.5% deviation over 24-hour sampling period;

·           incorporated with an electronic mass flow rate controller or other equivalent devices;

·           equipped with a flow recorder for continuous monitoring;

·           provided with a peaked roof inlet;

·           incorporated with a manometer;

·           able to hold and seal the filter paper to the sampler housing at horizontal position;

·           easy to change the filter; and

·           capable of operating continuously for a 24-hour period.

The ET shall provide the monitoring equipment, and ensure that sufficient number of HVS with appropriate calibration kit is available for carrying out the baseline, regular impact monitoring and ad-hoc monitoring.  The HVS shall be equipped with an electronic mass flow controller and be calibrated against a traceable standard at regular intervals, in accordance with requirements stated in the manufacturers operating manual.  All the equipment, calibration kit, filter papers, etc, shall be clearly labelled.

The flow rate of each HVS with mass flow controller shall be calibrated using an orifice calibrator.  Initial calibration of the dust monitoring equipment shall be conducted upon installation and prior to commissioning.  Five-point calibration shall be carried out every two months.  The transfer standard shall be traceable to the internationally recognised primary standard and be calibrated annually.  The concern parties such as IEC shall properly document the calibration data for future reference.  All the data shall be converted into standard temperature and pressure condition.

The flow-rate of the HVS before and after the sampling exercise with the filter in position shall be verified to be constant and be recorded on the data sheet.

If the ET proposes to use a direct reading dust meter to measure 1-hour TSP levels, he shall submit sufficient information to the ER and IEC to prove that the instrument is capable of achieving a comparable result to the HVS.  The instrument shall also be calibrated regularly, and the 1-hour sampling shall be determined periodically by the HVS to check the validity and accuracy of the results measured by direct reading method.

3.4.1                                Laboratory Measurement/ Analysis

A clean laboratory with constant temperature and humidity control, and equipped with the necessary measuring and conditioning instruments to handle the dust samples, shall be available for sample analysis and equipment calibration and maintenance.  The laboratory shall be either a HOKLAS-accredited or an internationally accredited laboratory.

If a site laboratory is set up or a non-HOKLAS accredited laboratory is hired for carrying out the laboratory analysis, the laboratory equipment shall be approved by the ER and the measurement procedures shall be witnessed by the IEC.  Any measurement performed by the laboratory shall be demonstrated to the satisfaction of the ER and IEC.  IEC shall regularly audit the measurement performed by the laboratory to ensure the accuracy of measurement results.  The ET Leader shall provide the ER with one copy of the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B for his reference.

Filter paper of size 8”x10” shall be labelled before sampling.  It shall be a clean filter paper with no pin holes, and shall be conditioned in a humidity controlled chamber for over 24-hr and be pre-weighed before use for the sampling.

After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper is then returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with a readout down to 0.1 mg.  The balance shall be regularly calibrated against a traceable standard.

All the collected samples shall be kept in a good condition for 6 months before disposal.

3.5                                      Monitoring Frequency

3.5.1                                Baseline Monitoring

Baseline monitoring shall be carried out to determine the ambient 24-hour and 1-hr TSP levels at the designated monitoring stations prior to the commencement of the construction works.  Continuous 24-hour TSP monitoring and 3 sets of 1-hour TSP monitoring shall be carried out daily for a period of at least two weeks.  General meteorological conditions and notes regarding any significant adjacent dust producing sources shall also be recorded throughout the baseline monitoring period.

Before commencing the baseline monitoring, the ET shall inform the Contractor, ER, IEC and EPD of the baseline monitoring schedule such that relevant parties may conduct on-site audit of the baseline monitoring.

During the baseline monitoring, there shall not be any construction or dust generating activities in the vicinity of the monitoring stations.

In case the baseline monitoring could not be carried out at the designated monitoring location during the baseline monitoring period, the ET shall carry out the monitoring at alternative location which could effectively represent the baseline conditions at the impact monitoring locations.  The alternative baseline monitoring location shall be agreed with the ER, IEC and EPD.

In exceptional cases, when insufficient baseline monitoring data or questionable results are obtained, the ET shall liaise with the ER, IEC and EPD to agree on an appropriate set of data to be used as a baseline reference.

The baseline monitoring shall provide data for the determination of the appropriate Action Levels with the Limit Levels set against statutory or otherwise agreed limits.

3.5.2                                Impact Monitoring

The ET shall carry out impact monitoring throughout the construction works.  24-hour TSP monitoring shall be conducted at least once in every six days at all the designated monitoring stations.  For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days shall be undertaken when the highest dust impact occurs.  Before commencing the monitoring, the ET shall inform the IEC of the monitoring schedule such that the IEC can conduct on-site audit to ensure accuracy of the monitoring results.

The specific time to start and stop the 24-hour TSP monitoring shall be clearly defined for each location and be strictly followed by the operator.

In case of non-compliance with the air quality criteria, more frequent monitoring, as specified in the EAP shall be conducted.

This additional monitoring shall be continued until the excessive dust emission or the deterioration in air quality is rectified.

3.6                                      Environmental Compliance and EAP

The baseline monitoring results form the basis for determining the A/L Levels for the impact monitoring.  The ET shall compare the impact monitoring results of 24-hour TSP and 1-hour TSP against the agreed A/L Levels as listed in Table 3.2.

Table 3.2        Action and Limit Levels for Construction Dust Monitoring

Parameter

Action Level

Limit Level

24-hour TSP Level in µgm-3

·       For baseline Level <= 200µg m-3, the Action Level = (Baseline level *1.3 + Limit Level) / 2

·       For baseline Level >200µg m-3, the Action Level = Limit Level

260µg m-3

1-hour TSP Level in µgm-3

·       For baseline Level <= 384µg m-3, the Action Level = (Baseline level *1.3 + Limit Level) / 2

·       For baseline Level >384µg m-3, the Action Level = Limit Level

500µg m-3

Should non-compliance or exceedance of the A/L Levels occur, actions in accordance with the EAP in Table 3.3 shall be carried out.


Table 3.3        EAP for Construction Dust Monitoring

Event

Action

ET

IEC

ER

Contractor(s)

Action Level being exceeded by one sampling day

1.     Repeat in-situ measurement to confirm findings;

2.     Identify source(s) of impact;

3.     Inform the Contractor(s), the ER, IEC and EPD within 24 hours;

4.     Check monitoring data, plant, equipment and the Contractor(s)’s working methods;

5.     Repeat measurement to confirm finding;

6.     Discuss mitigation measures with the Contractor(s);

1.     Check monitoring data submitted  by ET;

2.     Check Contractor’s working method.

1.       Discuss with the Contractor on the proposed mitigation measures;

2.       Make agreement on the mitigation measures to be implemented.

1.    Rectify unacceptable practice;

2.    Check working methods, plant and equipment;

3.    Consider changes of working methods;

4.    Discuss with the ET and propose mitigation measures to the ER;

5.    Implement the agreed mitigation measures.

Action Level being exceeded by more than one consecutive sampling days

1.     Repeat in-situ measurement to confirm findings;

2.     Identify source(s) of impact;

3.     Inform the Contractor(s), the ER, IEC and EPD;

4.     Check monitoring data, plant, equipment and Contractor(s)’s working methods;

5.     Repeat measurement to confirm finding;

6.     Discuss mitigation measures with the Contractor(s);

7.     Confirm mitigation measures are implemented;

8.     If exceedance continues, arrange meeting with IEC and RE.

1.     Check monitoring data submitted by ET;

2.     Check Contractor’s working method;

3.     Discuss with ET and Contractor on possible remedial measures;

4.     Advise the ET on the effectiveness of the proposed remedial measures;

5.     Supervise implementation of remedial measures.

1.     Discuss with the ET on the proposed mitigation measures;

2.     Make agreement on the mitigation measures to be implemented;

3.  Assess effectiveness of the implemented mitigation measures

1.    Rectify unacceptable practice;

2.    Check working methods, plant and equipment;

3.    Consider changes of working methods;

4.    Discuss with the ET and propose mitigation measures to the ER within 3 working days;

5.    Implement the agreed mitigation measures.

Limit Level being exceeded by one consecutive sampling day

1.   Repeat in-situ measurement to confirm findings;

2.   Identify source(s) of impact;

3.   Inform the Contractor(s), the ER, IEC and EPD;

4.   Check monitoring data, plant, equipment and the Contractor(s)’s working methods;

5.  Repeat measurement to confirm finding;

6.   Discuss mitigation measures with the ER and the Contractor(s);

7.   Confirm mitigation measures are implemented;

 

1.   Check monitoring data submitted by ET;

2.   Check Contractor’s working method;

3.   Discuss with ET and Contractor on possible remedial measures;

4.   Advise the ET on the effectiveness of the proposed remedial measures;

5.  Supervise implementation of remedial measures.

 

1.   Discuss with the ET and the Contractor(s) on the proposed mitigation measures;

2.   Request the Contractor(s) to critically review the working methods;

3.   Make agreement on the mitigation measures to be implemented;

4.    Assess the effectiveness of the implemented mitigation measures.

1.    Immediate stoppage of works;

2.   Confirm notification of the exceedance in writing;

3.    Rectify unacceptable practice;

4.    Check plant and equipment;

5.    Consider changes of working methods;

6.    Discuss with the ET, the ER and propose mitigation measures to the ER within 3 working days;

7.   Implement the agreed mitigation measures.

Limit Level being exceeded by more than one consecutive sampling days

1.  Repeat in-situ measurement to confirm findings;

2.  Identify source(s) of impact;

3.  Inform the Contractor(s), the ER, IEC and EPD;

4.  Check monitoring data, plant, equipment and Contractor(s)’s working methods;

5.  Repeat measurement to confirm finding;

6.  Discuss mitigation measures with the ER and the Contractor(s);

7.  Confirm mitigation measures are implemented;

 

1.   Check monitoring data submitted by ET;

2.   Check Contractor’s working method;

3.   Discuss amongst the ER, ET and Contractor on possible remedial measures;

4.   Review Contractor’s remedial actions whenever necessary to assure their effectiveness and advise the ER accordingly;

5.  Supervise implementation of remedial measures.

 

1.  Discuss with the ET and the Contractor(s) on the proposed mitigation measures;

2.  Request Contractor(s) to critically review working methods;

3.  Make agreement on the mitigation measures to be implemented;

4.  Assess effectiveness of the implemented mitigation measures;

5.  Consider and instruct, if necessary, the Contractor(s) to slow down or to stop all or part of the marine work until no exceedance of Limit Level.

1.  Immediate stoppage of works;

2.  Confirm notification of the exceedance in writing;

3.  Rectify unacceptable practice;

4.  Check plant and equipment;

5.  Consider changes of working methods;

6.  Discuss with the ET and the ER and propose mitigation measures to the ER within 3 working days;

7.  Implement the agreed mitigation measures;

8.  As directed by the ER, slow down or stop all or part of the construction activities.


4                                            NOISE

4.1                                      Introduction

The requirements, methodology, equipment, monitoring locations, criteria and protocols for the monitoring and audit of noise impacts during construction of the Project are presented in this section.  Noise monitoring is required during the construction phase of the River Modification Works.  The mitigation measures recommended to control noise impacts are summarised in Annex A.

4.2                                      Methodology and Criteria

Noise measurements should be carried out in accordance with the guidelines given in Annex – General Calibration and Measurement Procedures of Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM).

Whilst the Noise Control Ordinance (NCO) does not provide for the statutory control of construction activities occurring on weekdays during normal working hours (ie Monday to Saturday inclusive 0700-1900 hours), a daytime standard of Leq(30min) 75dB(A) as stipulated in Annex 5 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) will be adopted as the noise criterion for all residential dwellings; while a daytime standard of Leq(30min) 70dB(A) will be adopted for all educational institutions during normal school days and Leq(30min) 65dB(A) during examination periods.

The construction noise levels will be measured in terms of A-weighted equivalent continuous sound pressure level (Leq) measured in decibels dB(A).  Leq(30min) should be used as the monitoring parameter for the time period between 0700-1900 hours on normal weekdays. 

Supplementary information for data auditing, two statistical sound levels L10 and L90; the levels exceeded for 10 and 90 percent of the time respectively, should also be recorded during the monitoring for reference.  A sample data record sheet is shown in Annex C for reference.

Noise measurements should generally not be made in the presence of fog, rain, wind with a steady speed exceeding 5m s-1 or wind with gusts exceeding 10m s-1.  The wind speed should be checked with a portable wind speed meter capable of measuring the wind speed in ms-1.

4.3                                      Monitoring Equipment

As referred to the GW-TM, sound level meters in compliance with the International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1) Specifications should be used for carrying out the noise monitoring.  Immediately prior to and following each noise measurement the accuracy of the sound level meter should be checked using an acoustic calibrator generating a known sound pressure level at a known frequency.  Measurements may be accepted as valid only if the calibration levels from before and after the noise measurement agree to within 1.0 dB.

The ET should ensure that the equipment is maintained in a good working order in accordance with the manufacturer's recommendations with sufficient spare equipment available in the event of breakdown to maintain the planned monitoring programme.

The ET is responsible for the provision of the monitoring equipment and will ensure that sufficient noise measuring equipment and associated instrumentation are available for carrying out the baseline monitoring and impact monitoring.  All the equipment and associated instrumentation will be clearly labelled.

4.4                                      Monitoring Locations

Representative locations were selected to monitor the noise levels from the construction of the Project.  The noise monitoring stations are listed in Table 4.1 and presented in Figure 3.1.

Table 4.1        Noise Monitoring Stations for Construction Noise

Monitoring Station

Description

NM1

Ta Kwu Ling Village

NM2

Kaw Liu Village

The status and locations of noise sensitive receivers (NSRs) may change after issuing this Manual and the location of the noise monitoring station may need to be adjusted accordingly.  If such changes occur, the ET should propose an updated monitoring location for the agreement from the ER, IEC and EPD.

When alternative monitoring location is proposed, the following criteria, as far as practicable, should be followed:

·           At locations close to the major site activities which are likely to have noise impacts;

·           Close to the NSRs; and

·           For monitoring locations located in the vicinity of the NSRs, care should be taken to minimise disturbance to the occupants during monitoring.

The monitoring station will normally be at a point 1m from the exterior of the NSR building façade and at a height of approximately 1.2m above ground or at the height that has the least obstructed view of the construction activities in relation to the NSR.  If access to the normal monitoring position cannot be obtained, an alternative position will be chosen, and a correction to the measurements should be made, if appropriate.  For instance, a correction of +3 dB(A) should be made to free-field measurements.  The ET should agree with the ER, IEC, EPD and the owners/occupants of the premises on the monitoring position.  Once the positions for the monitoring stations are chosen, the baseline monitoring and the impact monitoring should be carried out at the same positions.

4.5                                      Baseline Monitoring

The ET should carry out baseline noise monitoring prior to the commencement of any construction works.  The baseline monitoring shall be measured for a continuous period of at least 14 consecutive days at a minimum logging interval of 30 minutes for day-time and 15 minutes (as three consecutive Leq(5min) readings) for evening, holidays and night-time.

Before commencing the baseline monitoring, ET shall inform the Contractor(s), IEC, ER and the EPD of the baseline monitoring schedule programme such that relevant parties could conduct on-site audit to ensure accuracy of the baseline monitoring results.

During the baseline monitoring, there should not be any construction activities in the vicinity of the monitoring stations.  Any non-Project related construction activities in the vicinity of the stations during the baseline monitoring should be noted and the source(s) and location(s) be recorded.

In case the baseline monitoring could not be carried out at any of the designated monitoring locations during the baseline monitoring period, the ET shall carry out the monitoring at alternative location which could effectively represent the baseline conditions at the impact monitoring locations.  The alternative baseline monitoring locations shall be agreed with the ER, Contractor(s) and IEC and approved by EPD.

In exceptional cases, when insufficient baseline monitoring data or questionable results are obtained, the ET shall liaise with the ER, IEC and EPD to agree on an appropriate set of data to be used as a baseline reference.

4.6                                      Impact Monitoring

Noise monitoring shall be carried out at all the designated monitoring stations.  An initial guide on the monitoring is to obtain one set of 30-minute measurement at each station between 0700 and 1900 hours on normal weekdays at a frequency of once a week when construction activities are underway.

If construction works are extended to include works during the hours between 1900 and 0700 hours of the following day, or on general holidays and Sundays, applicable Construction Noise Permits (CNPs) will be obtained by the Contractor(s) under the NCO requirements, and the frequency and scope of monitoring will be determined by EPD in the capacity of the Noise Control Authority (NCA).

4.7                                      Environmental Quality Performance Limits

A/L Levels provide an appropriate framework for the interpretation of monitoring results.  Interpretation of monitoring results is undertaken through checking them against the A/L Levels defined in Table 4.2.

Table 4.2        Action and Limit Level for Construction Noise Monitoring

Time Period

Action Level

Limit Level

0700 – 1900 hours on normal weekdays

When one documented complaint is received from any one of the sensitive receivers

75 dB(A) (Note) 

Notes:

(a)        Acceptable Noise Levels for Area Sensitivity Rating of A/B/C. Limit Level is reduced to 70dB(A) for schools and 65dB(A) during school examination periods.

(b)        If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the NCA have to be followed.

To account for cases where ambient noise levels, as identified by baseline monitoring, approach or exceed the stipulated Limit Level prior to commencement of construction, a Maximum Acceptable Impact Level, which incorporates the baseline noise level and the identified construction noise Limit Level, might be defined upon agreement with the EPD.  This amended level will, therefore, be greater than 75 dB(A) and will represent the maximum acceptable noise level at a specific monitoring station.

For compliance checking, after taking into account any adjustments agreed with EPD, comparison with either the Limit or the Maximum Acceptable Impact Level will represent the governing criteria for noise impact assessment during impact monitoring.

4.8                                      Event and Action Plan

The ET should compare the impact monitoring results with the noise criteria as defined in Table 4.2.  In cases where exceedance of these criteria occurs, actions should be carried out in accordance with the EAP shown in Table 4.3.


Table 4.3        Event and Action Plan for Construction Noise

Event

Action

 

ET

IEC

ER

Contractor

Action Level

1. Notify IEC and Contractor;

2. Carry out investigation;

3. Report the results of investigation to the IEC, ER and Contractor;

4. Discuss with the Contractor and formulate remedial measures;

5. Increase monitoring frequency to check mitigation effectiveness.

 

1. Review the analysed results submitted by the ET;

2. Review the proposed remedial measures by the Contractor and advise the ER accordingly;

3. Supervise the implementation of remedial measures.

 

1. Confirm receipt of notification of failure in writing;

2. Notify Contractor;

3. Require Contractor to propose remedial measures for the analysed noise problem;

4. Ensure remedial measures are properly implemented.

 

1. Submit noise mitigation proposals to IEC;

2. Implement noise mitigation proposals.

 

Limit Level

1. Identify source;

2. Inform IEC and ER:

3. Repeat measurements to confirm findings;

4. Increase monitoring frequency;

5. Carry out analysis of Contractor's working procedures to determine possible mitigation to be implemented;

6. Inform IEC, ER and EPD the causes and actions taken for the exceedances;

7. Assess effectiveness of Contractor's remedial actions and keep IEC, EPD and ER informed of the results;

8. If exceedance stops, cease additional monitoring.

 

1. Discuss amongst ER, ET, and Contractor on the potential remedial actions;

2. Review Contractors remedial actions whenever necessary to assure their effectiveness and advise the ER accordingly;

3. Supervise the implementation of remedial measures.

 

1. Confirm receipt of notification of failure in writing;

2. Notify Contractor;

3. Require Contractor to propose remedial measures for the analysed noise problem;

4. Ensure remedial measures properly implemented;

5. If exceedance continues, consider what portion of the work is responsible and instruct the Contractor to stop that portion of work until the exceedance is abated.

1.  Take immediate action to avoid further exceedance;

2. Submit proposals for remedial actions to IEC within 3 working days of notification;

3. Implement the agreed proposals;

4. Resubmit proposals if problem still not under control;

5. Stop the relevant portion of works as determined by the ER until the exceedance is abated.


4.9                                      Audit Requirements

It is necessary to undertake regular environmental audits and site inspections to ensure those recommended mitigation measures were properly implemented.  The requirements of the environmental audit programme were set out in Section 10 of the Manual.

The audit programme will verify the implementation status and evaluate the effectiveness and stability of the mitigation measures.

 


5                                            Water Quality

5.1                                      Introduction

This section presents details of the water quality monitoring to be undertaken during the construction and operation of the Project.  Water quality assessment carried out for the EIA indicates that the potential water quality impacts associated with the construction and operation of the Project will be within acceptable levels and no adverse water quality impacts are expected.  However, the monitoring programme is designed to verify the predictions of the EIA and ensure compliance with the assessment criteria. 

In accordance with the recommendations of the EIA, mitigation measures have been proposed during the construction and operation phases of the Project.  Details of the mitigation measures are presented in Annex A - Implementation Schedule.

5.2                                      Construction Phase

5.2.1                                General

Based on the construction methodology, the sediment will be excavated in dry within cofferdam.  Water quality monitoring is thus recommended during the foundation pit drainage and cofferdam demolition activities where there is a potential for the release of suspended solids (SS).

Water quality assessment for the construction phase of the Project indicates that the above construction activities may potentially lead to dispersion of suspended sediments to area downstream of the Project Site and hence causing elevated concentration of SS in river water.  However, the level of SS is predicted to be within acceptable levels (SS concentrations caused by construction activity at 500 m upstream and 1,000 m downstream of the work area would be less than 130% of baseline SS concentrations ) and will not lead to any adverse water quality impacts to the identified water sensitive receivers (WSRs).  The Water Quality Impact Monitoring which will be undertaken during construction of the Project will be designed to verify these predictions.

In addition to the Water Quality Impact Monitoring, Baseline Water Quality Monitoring will also be undertaken for the Project to determine the Action and Limit Levels for the monitoring programme.

5.2.2                                Water Quality Impact Monitoring

During construction phase of the Project, Water Quality Impact Monitoring will be undertaken at the following locations when construction works mentioned in Section 5.2.1 above are in progress:

During Foundation Pit Drainage and Cofferdam Demolition at Work Area I and Work Area II

·           500 m upstream of Work Area I; and

·           1,000 m downstream of Work Area II.

During Foundation Pit Drainage and Cofferdam Demolition at Work Area III and Work Area IV

·           500 m upstream of Work Area III; and

·           1,000 m downstream of Work Area IV.

There will be one monitoring station at each location (ie a total of four monitoring stations).  Monitoring will be conducted for three times per week during the construction period.  The interval between two sampling surveys will not be less than 36 hours.  During each sampling survey, water samples for laboratory analysis and in situ measurements will be taken at all monitoring stations for the following water quality parameters:

·           Dissolved Oxygen (mg L-1) (in situ);

·           pH (in situ);

·           Turbidity (NTU) (in situ); and

·           Suspended Solids (mg L-1) (laboratory analysis).

Duplicate water samples and in situ measurements of the above parameters will be taken at mid-depth of each station during a sampling survey.  In addition to the above water quality parameters, other relevant data will also be measured and recorded in the Water Quality Impact Monitoring Logs, including the location of the sampling stations, water depth, time, weather conditions, special phenomena and work activities undertaken around the monitoring and works area that may influence the monitoring results.

Upon completion of all construction activities, a post-project water quality monitoring will be carried out for four weeks in the same manner as the Water Quality Impact Monitoring.

5.2.3                                Baseline Water Quality Monitoring

Baseline Water Quality Monitoring will be conducted for a period of four weeks prior to the commencement of construction works mentioned in Section 5.2.1 above in order to gather representative water quality data for the EM&A programme.   Location and number of baseline monitoring stations will be the same as the Water Quality Impact Monitoring.

Baseline Water Quality Monitoring will be undertaken for three days per week at all stations.  The interval between two sampling surveys will not be less than 36 hours. 

The following suite of parameters will be measured as part of the Baseline Water Quality Monitoring:

·           Dissolved Oxygen (mg L-1) (in situ);

·           pH (in situ);

·           Turbidity (NTU) (in situ); and

·           Suspended Solids (mg L-1) (laboratory analysis).

Duplicate water samples and in situ measurements of the above parameters will be taken at mid-depth of each station during a survey.  In addition to the above water quality parameters, other relevant data will also be measured and recorded in the Baseline Water Quality Monitoring, including the location of the sampling stations, water depth, time, weather conditions, special phenomena and work activities undertaken around the monitoring and works area that may influence the monitoring results.

5.2.4                                Water Quality Compliance and Event & Action Plan

Results of the Water Quality Impact Monitoring will be evaluated against Action and Limit Levels.  Suspended solids (SS) will be the key parameter under evaluation and Action and Limit Levels will be determined for this parameter.  However, turbidity and dissolved oxygen can also provide valuable instantaneous information on water quality and thus Action and Limit Levels are measured for these parameters to facilitate quick responsive action in the event of any apparent unacceptable deterioration attributable to the works.

The Action and Limit Levels for SS, turbidity and dissolved oxygen will be determined according to the criteria shown in Table 5.1.  Action and Limit Levels are used to determine whether modifications are necessary to mitigate impacts to water quality.  In the event that the levels are exceeded, appropriate actions in the Event and Action Plan (Table 5.2) should be undertaken. 

Table 5.1        Determination of Action and Limit Levels

Parameter

Action Level

Limit Levels

Suspended Solids

The average value measured at the monitoring station are >120% of baseline data

 

The average value measured at the monitoring station are >130% of baseline data

 

Turbidity

The average value measured at the monitoring station are >95%ile of baseline data

The average value measured at the monitoring station are >99% of baseline data

Dissolved Oxygen

The average value measured at the monitoring station are <5%-ile of baseline data

The average value measured at the monitoring station are <1%-ile of baseline data

 


Table 5.2        Water Quality Event and Action Plan

Event

ET Leader

IEC

ER

Contractor

Action level being exceeded by one sampling day

·          Repeat in-situ measurement to confirm findings;

·          Identify source(s) of impact;

·          Inform IEC and Contractor;

·          Check monitoring data, all plant, equipment and Contractor's working methods;

·          Discuss mitigation measures with IEC and Contractor;

·          Repeat measurement on next day of exceedance.

·          Discuss with ET and Contractor on the mitigation measures;

·          Review proposals on mitigation measures submitted by Contractor and advise the ER accordingly;

·          Assess the effectiveness of the implemented mitigation measures.

·          Discuss with IEC on the proposed mitigation measures;

·          Make agreement on the mitigation measures to be implemented.

·          Inform the ER and confirm notification of the non-compliance in writing;

·          Rectify unacceptable practice;

·          Check all plant and equipment

·          Consider changes of working methods;

·          Discuss with ET and IEC and propose mitigation measures to IEC and ER;

·          Implement the agreed mitigation measures.

Action level being exceeded by more than one consecutive sampling days

·          Repeat in-situ measurement to confirm findings;

·          Identify source(s) of impact;

·          Inform IEC and Contractor;

·          Check monitoring data, all plant, equipment and Contractor's working methods;

·          Discuss mitigation measures with IEC and Contractor;

·          Ensure mitigation measures are implemented;

·          Prepare to increase the monitoring frequency to daily;

·          Repeat measurement on next day of exceedance.

·          Discuss with ET and Contractor on the mitigation measures

·          Review proposals on mitigation measures submitted by Contractor and advise the ER accordingly

·          Assess the effectiveness of the implemented mitigation measures.

·          Discuss with IEC on the proposed mitigation measures;

·          Make agreement on the mitigation measures to be implemented;

·          Assess the effectiveness of the implemented mitigation measures.

·          Inform the Engineer and confirm notification of the non-compliance in writing;

·          Rectify unacceptable practice;

·          Check all plant and equipment;

·          Consider changes of working methods;

·          Discuss with ET and IEC and propose mitigation measures to IEC and ER within 3 working days;

·          Implement the agreed mitigation measures.

Limit level being

exceeded by one

sampling day

·          Repeat in-situ measurement to confirm findings;

·          Identify source(s) of impact;

·          Inform IEC, contractor and EPD;

·          Check monitoring data, all plant, equipment and Contractor's working methods;

·          Discuss mitigation measures with IEC, ER and Contractor;

·          Ensure mitigation measures are implemented;

·          Increase the monitoring frequency to daily until no exceedance of Limit level.

·          Discuss with ET and Contractor on the mitigation measures;

·          Review proposals on mitigation measures submitted by Contractor and advise the ER accordingly;

·          Assess the effectiveness of the implemented mitigation measures.

·          Discuss with IEC, ET and Contractor on the proposed mitigation measures;

·          Request Contractor to critically review the working methods;

·          Make agreement on the mitigation measures to be implemented;

·          Assess the effectiveness of the implemented mitigation measures.

·          Inform the Engineer and confirm notification of the non-compliance in writing;

·          Rectify unacceptable practice;

·          Check all plant and equipment;

·          Consider changes of working methods;

·          Discuss with ET , IEC and ER and propose mitigation measures to IEC and ER within 3 working days;

·          Implement the agreed mitigation measures.

Limit level being

exceeded by more

than one

consecutive

sampling days

·          Repeat in-situ measurement to confirm findings;

·          Identify source(s) of impact;

·          Inform IEC, contractor and EPD;

·          Check monitoring data, all plant, equipment and Contractor's working methods;

·          Discuss mitigation measures with IEC, ER and Contractor;

·          Ensure mitigation measures are implemented;

·          Increase the monitoring frequency to daily until no exceedance of Limit level for two consecutive days.

·          Discuss with ET and Contractor on the mitigation measures;

·          Review proposals on mitigation measures submitted by Contractor and advise the ER accordingly;

·          Assess the effectiveness of the implemented mitigation measures.

·          Discuss with IEC, ET and Contractor on the proposed mitigation measures;

·          Request Contractor to critically review the working methods;

·          Make agreement on the mitigation measures to be implemented;

·          Assess the effectiveness of the implemented mitigation measures;

·          Consider and instruct, if necessary, the Contractor to slow down or to stop all or part of the works until no exceedance of Limit level.

·          Inform the ER and confirm notification of the non-compliance in writing;

·          Rectify unacceptable practice;

·          Check all plant and equipment;

·          Consider changes of working methods;

·          Discuss with ET , IEC and ER and propose mitigation measures to IEC and ER within 3 working days;

·          Implement the agreed mitigation measures;

·          As directed by the Engineer, to slow down or to stop all or part of the works or construction activities..


5.2.5                                Equipment

The following equipment will be supplied and used by the contractor for the water quality monitoring:

·           Positioning Device - A hand-held digital Global Positioning System (GPS) with way point bearing indication or other equivalent instrument of similar accuracy will be provided and used during monitoring to ensure the monitoring team is at the correct location before taking measurements.

·           Dissolved Oxygen and Temperature Measuring Equipment - The instrument will be a portable, weatherproof dissolved oxygen measuring instrument complete with cable, sensor, comprehensive operation manuals, and will be operable from a DC power source.  It will be capable of measuring: dissolved oxygen levels in the range of 0 - 20 mg L-1 and 0 - 200% saturation; and a temperature of 0 - 45 degrees Celsius.

It will have a membrane electrode with automatic temperature compensation complete with a cable.  Sufficient stocks of spare electrodes and cables will be available for replacement where necessary (for example, YSI model 59 metre, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved similar instrument).

·           Turbidity Measurement Equipment - The instrument will be a portable, weatherproof turbidity-measuring unit complete with cable, sensor and comprehensive operation manuals.  The equipment will be operated from a DC power source, it will have a photoelectric sensor capable of measuring turbidity between 0 - 1000 NTU (Hach 2100P or an approved similar instrument).

·           pH meter – A portable pH meter capable of measuring a range between 0.0 and 14.0 will be provided to measure pH in marine waters.

·           Water Sampler- A water sampler (eg Kahlsico Water Sampler), which is a transparent PVC cylinder (capacity not less than 2 litres) and can be effectively sealed with latex cups at both ends, will be used for sampling.  The sampler will have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth.  Water samples for suspended solids measurement will be collected in high density polythene bottles, packed in ice (cooled to 4 ºC without being frozen), and delivered to the laboratory in the same day as the samples were collected.

·           Water Depth Gauge - A portable, battery-operated echo sounder will be used for the determination of water depth at each designated monitoring station. 

5.2.6                                Sampling / Testing Protocols

All in situ monitoring instruments will be checked, calibrated and certified by a laboratory accredited under HOKLAS or any other international accreditation scheme before use, and subsequently re-calibrated at three month intervals throughout the stages of the water quality monitoring.  Responses of sensors and electrodes will be checked with certified standard solutions before each use.

On-site calibration of field equipment will follow the “Guide to Field and On-Site Test Methods for the Analysis of Waters”, BS 1427: 1993.  Sufficient stocks of spare parts will be maintained for replacements when necessary.  Backup monitoring equipment will also be made available so that monitoring can proceed uninterrupted even when equipment is under maintenance, calibration etc.

Water samples for SS measurements will be collected in high density polythene bottles, packed in ice (cooled to 4° C without being frozen), and delivered to a HOKLAS laboratory as soon as possible after collection.

5.2.7                                Laboratory Procedures

The analytical techniques to be adopted for this Project must conform to HOKLAS (or similar overseas) accreditation.  Using chain of custody forms, collected water samples will be transferred directly to laboratory for immediate processing.  Laboratory analysis for SS will started within 24 hours after collection of water samples.

5.2.8                                QA/QC

Field Logs

Field logs will be maintained for all survey work, noting the date of the survey, equipment used, survey manager and a record of all activities and observations.  Field logs will be retained for the duration of the Project and archived on completion.

In situ measured data will be digitally recorded from the instruments and converted into Microsoft Excel format, or manually noted.  Both disc copy and hard copy will be retained for the file records.  Any deviation from the standard procedure will be noted in the log and the reason for the deviation recorded.  In addition, field logs will contain notes of events or activities in the vicinity of the monitoring location which might give rise to anomalous data being recorded.

Sampling

The Contractor will record all data from in situ testing and from any analysis carried out in a Field Log.  All samples will be identified with a unique date/time/location/depth/sample-type code which will be attached to the sample container or written in indelible ink directly on the container.  In order to avoid contamination of the samples, all containers will be new and unused and of analytical grade quality.  Sources of contamination will be isolated from the working area and any sample contaminated by local material will be discarded and the sampling repeated. 

Measurement Procedures

All in situ monitoring instruments will be checked, calibrated and certified and subsequently re-calibrated at three monthly intervals throughout all stages of the water quality monitoring, or as required by the manufactures specification.  Certificate(s) of Calibration specifying the instrument will be attached to the monitoring reports. 

Transport of Samples

All samples transferred from one sub-contractor to another will be accompanied by Chain of Custody (COC) forms.  Any missing or damaged samples require notification to ET Leader following logging in the laboratory QA system.  The number of samples, the parameters to be tested and the time of delivery should be clearly stated on the COC forms to ensure that samples are analysed for the correct parameters and suitable time is provided to the analytical laboratory for provision of resources required in the analyses.

5.3                                      Operation Phase

Adverse water quality impact is not expected during operation phase and hence monitoring is not considered necessary.  In fact the water quality will be monitored through the existing monitoring programme along Shenzhen River.

 


6                                            Ecology

6.1                                      Introduction

In accordance with the recommendations of the EIA, good construction practices have been proposed during the construction of the Project.  Details of the good practices are presented in Annex A - Implementation Schedule.  Regular site inspections during the construction phase will confirm the implementation of these practices and the adaptation of ecological design in the landscape work after the completion of construction.

6.2                                      Construction Phase

No ecological mitigation measures apart from the adoption of good construction practise are required to be checked as part of the EM&A procedures during the construction phase.  The list of good construction practices is provided in Annex A.

6.3                                      Operation Phase

The completed landscape works adopting ecological design on the Hong Kong side will be monitored during the one year establishment period. 

Although no adverse residual impacts are envisaged based on the results of impact assessment, wetland dependent bird monitoring for one year is recommended after the establishment of the landscape plantings of the Project.  The purpose of the operation monitoring is to review the performance of the reprovisioned/reinstated habitats.  Particular focus will be made on bird species of conservation interest (especially ardeid species including Chinese Pond Heron, Black-crowned Night Heron, Grey Heron, Great Egret, Intermediate Egret and Little Egret, and two wetland dependant species Common Teal and White-breasted Waterhen).

Standard, quantitative point count surveys will be undertaken at designated sampling locations at once per month after the establishment of the landscape plantings of the Project.  The necessity for further ecological monitoring would be reviewed after the first year ecological monitoring programme.  Locations of sampling transects shall include reprovisioned/reinstated habitats including riverbank landscape areas, floodplains and watercourse, and other reference locations within Hong Kong boundary.  Details of the monitoring programme will be formulated and further submitted under the Project.

 

7                                            Waste Management

7.1                                      Introduction

The Project is expected to generate the following types of waste during the construction phase:

·           Dredged river sediment;

·           Construction and demolition (C&D) materials;

·           Chemical waste;

·           Sewage; and

·           General refuse.

Dredged river sediment will be generated from maintenance dredging during the operation phase.

Mitigation measures, where appropriate, have been recommended in the EIA  Report to avoid or reduce potential adverse environmental impacts associated with handling, collection and disposal of waste arising from the construction and operation of the Project.

Waste management will be the Contractor(s)’s responsibility and wastes produced during the construction phase will be managed in accordance with appropriate waste management practices and EPD’s regulations and requirements.

Auditing of waste management practices during regular site inspections will confirm that these solid and liquid wastes generated during construction are not disposed of into the surrounding stormwater drains/river.  The Contractor(s) will be responsible for the implementation of any mitigation measures to reduce waste or redress issues arising from the waste materials. 

7.2                                      Waste Management Practices

The Contractor(s) shall incorporate the recommended mitigation measures into a Waste Management Plan (WMP) for managing the different types of wastes on site.  The Contractor(s) shall submit the WMP to DSD and the Engineer for approval prior to the commencement of the construction works.  The WMP will be prepared and implemented in accordance with ETWB TC(W) No. 19/2005 and shall be certified by the ET Leader and verified by the IEC as conforming to the information and recommendations contained in the Waste Management Impact Assessment and this Manual. 

The WMP shall describe the arrangements for avoidance, re-use, recover and recycling, storage, collection, treatment and disposal of different categories of waste to be generated from construction activities and shall include the recommended mitigation measures on waste management detailed in Annex A of this Manual.  The WMP shall indicate the disposal location(s) of all surplus excavated spoil and other wastes.

 

Prior to the commencement of dredging activities, the disposal strategy for the dredged sediment shall be determined in accordance with the ETWB TC(W) No. 34/2002: Management of Dredged/Excavated Sediment.

A Trip Ticket system shall be included in the WMP.  Surplus excavated spoil and other wastes shall not be disposed of at any other designated disposal locations unless otherwise approved in writing by EPD, Secretary of Public Fill Committee and/or other authorities, as appropriate.

The Implementation Schedule (see Annex A) provides details on the appropriate mitigation measures for avoiding and preventing adverse environmental impacts associated with dredged river sediment, C&D materials, chemical wastes, general refuse and sewage from the workforce.  The WMP shall be refined and updated as more detailed information is generated on the volume of dredged river sediment and the agreed disposal arrangements.  Similarly, it should be regularly reviewed, and updated as appropriate, throughout the course of the construction works to confirm that it remains current with the latest detailed information and works practices.

The WMP shall also outline the requirements for a waste audit programme to verify that the measures outlined in the plan are effectively implemented and adhered too.

7.3                                      Waste Management EM&A

To facilitate monitoring and control over the contractors’ performance on waste management, a waste inspection and audit programme will be implemented throughout the construction phase.  The programme shall look at the aspects of waste management including waste generation, storage, recycling, transport and disposal.  An appropriate audit programme shall be undertaken with the first audit conducted at the commencement of the construction works.

The aims of the waste inspection and audit programme are:

·           To review the Contractor’s WMP including the quantities and types of C&D materials generated, reused on-site and disposed of off-site; the amount of fill materials exported from/imported to the site and the quantity of timber used in temporary works construction for each process/activity;

·           To confirm that the wastes arising from works are handled, stored, collected, transferred and disposed of in an environmentally acceptable manner and comply with the relevant requirements under the Waste Disposal Ordinance (WDO) and its regulations;

·           To confirm that the Contractor(s) properly implements the appropriate environmental protection and waste pollution control mitigation measures, as outlined in the Implementation Schedule (see Annex A), to reduce and control the potential for waste impacts.

·           To monitor the implementation and achievement of the WMP on-site to assess its effectiveness; and

·           To monitor the follow-up action(s) on deficiencies identified.

 

Joint site inspections and audits by the ET, IEC and Contractor(s) shall be undertaken each month.  Particular attention will be given to the Contractor(s)’s provision of sufficient spaces, adequacy of resources and facilities for on-site sorting and temporary storage of C&D materials.  The C&D materials to be disposed of from the site shall be visually inspected.  The public fill for delivery to the government public fill reception facilities shall contain no observable non-inert materials (e.g. general refuse, timber, etc).  As a good practice, the waste to be disposed of at landfills should minimise any inert or reusable/recyclable C&D materials (e.g. soil, broken rock, metal, and paper/cardboard packaging, etc).  Any irregularities observed during the site audits will be raised promptly to the Contractor(s) for rectification.

The findings of the waste audits will be reported in the Monthly EM&A Reports.

7.3.1                                Methodology and Criteria

The Contractor(s) must confirm that the necessary disposal permits or licences are obtained from appropriate authorities in accordance with the various ordinances.  In addition to the monthly joint inspections/ audits, each Contractor(s) shall designate a member of staff as being responsible for routine inspections and audits of on-site waste management practices, with reference to the relevant legislation and guidelines as well as the recommendations given in the Implementation Schedule contained in Annex A of this Manual, and defined below:

General Legislation

·           Waste Disposal Ordinance (Cap 354);

·           Waste Disposal (Chemical Waste) (General) Regulation (Cap 354);

·           Waste Disposal (Charges for Disposal of Construction Waste) Regulation;

·           Land (Miscellaneous Provisions) Ordinance (Cap 28);

·           Public Health and Municipal Services Ordinance (Cap 132) – Public Cleansing and Prevention of Nuisances Regulations;

·           Dumping at Sea Ordinance (1995); and

·           The storage, handling and disposal of chemical waste should be audited with reference to the requirements of the Code of Practice on the Package, Labelling and Storage of Chemical Wastes published by the EPD.

Other Relevant Guidelines

·           Waste Disposal Plan for Hong Kong (December 1989), Planning, Environment and Lands Branch Government Secretariat, Hong Kong Government;

·           Chapter 9 – Environment (1999), Hong Kong Planning and Standards Guidelines, Hong Kong Government;

·           New Disposal Arrangements for Construction Waste (1992), Environmental Protection Department & Civil Engineering Department, Hong Kong Government;

·           Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes (1992), Environmental Protection Department, Hong Kong Government;

·           Works Branch Technical Circular (WBTC) No. 32/92, The Use of Tropical Hard Wood on Construction Site; Works Branch, Hong Kong Government;

·           WBTC No. 2/93, Public Dumps, Works Branch, Hong Kong Government;

·           WBTC No. 2/93B, Public Filling Facilities, Works Branch, Hong Kong Government

·           WBTC No. 16/96, Wet Soil in Public Dumps; Works Branch, Hong Kong Government;

·           WBTC Nos. 4/98 and 4/98A, Use of Public Fill in Reclamation and Earth Filling Projects; Works Bureau, Hong Kong SAR Government;

·           Waste Reduction Framework Plan, 1998 to 2007, Planning, Environment and Lands Bureau, Government Secretariat, 5 November 1998;

·           WBTC Nos. 25/99, 25/99A and 25/99C, Incorporation of Information on Construction and Demolition Material Management in Public Works Subcommittee Papers; Works Bureau, Hong Kong SAR Government;

·           WBTC No. 12/2000, Fill Management; Works Bureau, Hong Kong Government;

·           WBTC No. 19/2001, Metallic Site Hoardings and Signboards, Works Bureau, Hong Kong SAR Government;

·           WBTC Nos. 6/2002 and 6/2002A, Enhanced Specification for Site Cleanliness and Tidiness, Works Bureau, Hong Kong SAR Government;

·           WBTC No. 11/2002, Control of Site Crusher, Works Bureau, Hong Kong SAR Government;

·           WBTC No. 12/2002, Specification Facilitating the Use of Recycled Aggregates. Works Bureau, Hong Kong SAR Government;

·           ETWB TC(W) No. 33/2002, Management of Construction and Demolition Material Including Rock; Environment, Transport and Works Bureau, Hong Kong SAR Government;

·           ETWB TC(W) No. 34/2002, Management of Dredged/Excavated Sediment; Environment, Transport and Works Bureau, Hong Kong SAR Government;

·           ETWB TC(W) No. 31/2004, Trip Ticket System for Disposal of Construction & Demolition Materials, Environment, Transport and Works Bureau, Hong Kong SAR Government;

·           ETWB TC(W) No. 19/2005, Environmental Management of Construction Site, Environment, Transport and Works Bureau, Hong Kong SAR Government; and

·           WBTC No. 25/99A and 25/99C, Incorporation of Information on Construction and Demolition Material Management in Public Works Sub-committee Papers; Works Bureau, Hong Kong SAR Government.

The Contractor(s)’s waste management practices shall be audited with reference to the checklist detailed in Table 7.1.

7.4                                      Mitigation Measures

Details of the required mitigation measures are included within the Implementation Schedule of Annex A of this Manual.

 


Table 7.1      Waste Management Checklist

Activities

Timing

Checking Frequency

If non-compliance noted, Action Required

Necessary waste disposal permits or licences have been obtained

Before the commencement of works

Once

The ET will inform the Contractor(s) and DSD.  The Contractor(s) shall apply for the necessary permits/ licences prior to disposal of the waste.  The ET shall verify that corrective action has been taken.

Dredged sediments are managed and disposed in accordance with the ETWB TC(W) No. 34/2002: Management of Dredged/Excavated Sediment. 

Throughout the dredging works. Sediment assessment to be completed prior to dredging

Each Month

 

The ET shall inform the Contractor(s) and DSD.  DSD will instruct the Contractor(s) to manage and dispose the dredged materials properly.  The Contractor(s) will immediately suspend dredging until the dredging materials are properly managed and disposed.

Only licensed waste haulier are used for waste collection.

Throughout the works

Each Month

 

The ET shall inform the Contractor(s) and DSD.  DSD will instruct the Contractor(s) to use a licensed waste haulier.  The Contractor(s) shall temporarily suspend waste collection of that particular waste until a licensed waste haulier is used.  Corrective action shall be undertaken within 48 hours.

Records of quantities of wastes generated, recycled and disposed are properly kept.  For demolition material/waste, the number of loads for each day shall be recorded (quantity of waste can then be estimated based on average truck load.  For landfill charges, the receipts of the charge could be used for estimating the quantity).

Throughout the works

Each Month

 

The ET will inform the Contractor(s) and DSD.  The Contractor(s) shall estimate the missing data based on previous records and the activities carried out.  The ET shall review the results and forward to DSD for approval.

Wastes shall be removed from site in a timely manner.  General refuse is collected on a daily basis.

Throughout the works

Each Month

 

The ET shall inform the Contractor(s) and DSD.  DSD will instruct the Contractor(s) to remove waste accordingly.

Waste storage areas shall be properly cleaned and do not cause windblown litter and dust nuisance.

Throughout the works

Each Month

 

The ET shall inform the Contractor(s) and DSD.  DSD will instruct the Contractor(s) to clean the storage area and/or cover the waste.

Different types of waste shall be segregated in different containers or skips to enhance recycling of materials and proper disposal of waste.

Throughout the works

Each Month

 

The ET shall inform the Contractor(s) and DSD.  DSD will instruct the Contractor(s) to provide separate skips/ containers.  The Contractor(s) shall verify that the workers place the waste in the appropriate containers.

Chemical wastes shall be stored, handled and disposed of in accordance with the Code of Practice on the Packaging, Handling and Storage of Chemical Wastes, published by the EPD.

Throughout the works

Each Month

 

The ET shall inform the Contractor(s) and DSD.  DSD will instruct the Contractor(s) to rectify the issues immediately.  Warning will be given to the Contractor(s) if corrective actions are not taken within 24 hrs.

C&D materials shall be properly covered before leaving the site.

Throughout the works

Each Month

 

The ET shall inform the Contractor(s) and DSD.  DSD will instruct the Contractor(s) to comply.  The Contractor(s) shall confirm that the C&D materials are properly covered when transport out of the site.

Wastes shall be disposed at licensed sites.

Throughout the works

Each Month

 

The ET shall inform the Contractor(s) and DSD.  DSD will warn the Contractor(s) and instruct the Contractor(s) to confirm that the wastes are disposed of at the licensed sites.  Should it involve chemical waste, the Waste Control Group of EPD will be notified.

 

 

8                                            Cultural Heritage

8.1                                      Introduction

In accordance with the recommendations of the EIA, mitigation measure has been proposed during the construction phase of the Project where applicable. 

8.2                                      Archaeology

The archaeological survey identified only the secondary archaeological deposits at Chuk Yuen and Pak Fu Shan sections (i.e. Sections 2 and 4) of the Project.  The chance of finding in situ archaeological deposits is very low.  Thus no impact on significant archaeological resources is anticipated and no archaeological monitoring is required.  Other sections (i.e. Sections 1, 3 and 5) have been identified with no archaeological potential where no impact is anticipated.  Thus no archaeological monitoring is required.  Pursuant to the Antiquities and Monuments Ordinance, the project proponent should inform the AMO immediately in case of discovery of antiquities or supposed antiquities in the course of soil excavation works in construction stage.

However, it should be noted that the archaeological impact assessment covered only the works area assigned as at the date of this report.  If the works boundary changes in later stage to cover additional area not covered in the EIA, the need for further archaeological survey and subsequent impact assessment should be reviewed and AMO should be consulted.

8.3                                      Built Heritage

As no direct or indirect impacts on the identified built heritage sites are anticipated due to their large separation distance from the Project Site, no mitigation measures are considered necessary.  As such, no built heritage monitoring and audit is required. 



9                                            Landscape & visual

9.1                                      Introduction

The EIA has recommended that checking of implementation of the mitigation measures for landscape and visual resources shall be undertaken as part of the site inspections.  The implementation and maintenance of mitigation measures (see Annex A) shall be checked to confirm that they are fully realised and that potential conflicts between the proposed landscape measures and any other project works and operational requirements are resolved at the earliest practical date and without compromise to the intention of the mitigation measures. 

9.2                                      Construction Phase

In accordance with the recommendations of the EIA, landscape and visual mitigation measures have been proposed during the construction phase of the Project.  Details of the mitigation measures are presented in Annex A - Implementation Schedule which shall be checked as part of the EM&A procedures during the construction phase.

9.3                                      Operation Phase

The completed landscape works adopting ecological design on the Hong Kong side will be monitored during the one year establishment period.  No specific monitoring and audit programme is required for the ecological friendly design of the flood retardation pond within the Shenzhen boundary.

 

10                                        Environmental Site Inspection

10.1                                  Site Inspections

Site inspections provide a direct means to assess and confirm that the Contractor(s)’s environmental protection and pollution control measures are in compliance with the contract specifications.  The site inspection shall be undertaken routinely by the ET to verify that appropriate environmental protection and pollution control mitigation measures are properly implemented in accordance with the EIA.  In addition, the ET shall be responsible for defining the scope of the inspections, detailing any deficiencies that are identified, and reporting any necessary action or additional mitigation measures that were implemented as a result of the inspection. 

Regular site inspections shall be carried out by the ET each month.  The IEC shall also undertake monthly site audit to assess the performance of the Contractor(s).  The areas of inspection shall not be limited to the site area and shall also include the environmental conditions outside the site which are likely to be affected, directly or indirectly, by the site activities.  The ET shall make reference to the following information while conducting the inspections:

·           the EIA and EM&A recommendations on environmental protection and pollution control mitigation measures;

·           ongoing results of the EM&A programme;

·           work progress and programme;

·           individual works methodology proposals;

·           the contract specifications on environmental protection;

·           the relevant environmental protection and pollution control laws; and

·           previous site inspection results.

The Contractor(s) shall update the ET with relevant information on the construction works prior to carrying out the site inspections.  The site inspection results shall be submitted to the IEC, DSD and the Contractor(s) within 24 hours.  Should actions be necessary, the ET shall follow up with recommendations on improvements to the environmental protection and pollution control works and shall submit these recommendations in a timely manner to the IEC, DSD and the Contractor(s).  They shall also be presented, along with the remedial actions taken, in the monthly EM&A Report.  The Contractor(s) shall follow the procedures and time frame stipulated in the environmental site inspection for the implementation of mitigation proposal and the resolution of deficiencies in the Contractor(s)’ EMS.  An action reporting system shall be formulated and implemented to report on any remedial measures implemented subsequent to the site inspections.

Ad hoc site inspections shall also be carried out by the ET and site audits by the IEC if significant environmental issues are identified.  Inspections and audits may also be required subsequent to receipt of an environmental complaint or as part of the investigation work as specified in the EAPs for EM&A programme.

10.2                                  Compliance with Legal & Contractual Requirements

There are contractual environmental protection and pollution control requirements as well as environmental protection and pollution control laws in Hong Kong with which the construction activities will comply.

In order that the works are in compliance with the contractual requirements, the works method statements submitted by the Contractor(s) to DSD for approval will be sent to the ET for review.

The ET shall also review the progress and programme of the works to check the regulatory compliance.

The Contractor(s) shall regularly copy relevant documents to the ET so that the checking and auditing work can be carried out.  The relevant documents are expected to include at a minimum the updated Work Progress Reports, the updated Works Programme, the application letters for different licence/permits under the environmental protection laws and all valid licences/permits. The site diary shall also be available for the ET inspection upon request.

After reviewing the document, the ET shall advise the IEC, DSD and the Contractor(s) of any non-compliance from the contractual and legislative requirements on environmental protection and pollution control for follow-up actions.  The ET shall also advise the IEC, the Contractor(s) and DSD on the current status on licence/permit applications and any environmental protection and pollution control preparation works that may not be suitable for the works programme or may result in potential nonconformity of environmental protection and pollution control requirements.

Upon receipt of the advice, the Contractor(s) shall undertake immediate action to remedy the situation.  The ET, IEC and DSD shall follow up to confirm that appropriate action(s) shall be taken by the Contractor(s) in order that the environmental protection and pollution control requirements are fulfilled.

10.3                                  Environmental Complaints

The ET shall undertake the following procedures upon receipt of a complaint:

(i)      log complaint and date of receipt into the complaint database and inform the IEC immediately;

(ii)     investigate the complaint and discuss with the Contractor(s) and DSD to determine its validity and to assess whether the source of the issue is due to works activities;

(iii)     if a complaint is considered valid due to the works , the ET will identify mitigation measures in consultation with the Contractor(s), DSD and IEC;

(iv)    if mitigation measures are required, the ET shall advise the Contractor(s) accordingly;

(v)     review the Contractor(s)'s response on the identified mitigation measures and the updated situation;

(vi)    if the complaint is transferred from EPD, an interim report shall be submitted to EPD on the status of the complaint investigation and follow-up action within the time frame assigned by EPD;

(vii)    undertake additional monitoring and audit to verify the situation if necessary and confirm that any valid reason for complaint does not recur;

(viii)   report the investigation results and the subsequent actions on the source of the complaint for responding to complainant.  If the source of complaint is EPD, the results shall be reported within the time frame assigned by EPD; and

(ix)    record the complaint, investigation, the subsequent actions and the results in the monthly EM&A Reports.

During the complaint investigation work, the ET, Contractor(s) and DSD shall cooperate with the IEC in providing the necessary information and assistance for completion of the investigation.  If mitigation measures are identified in the investigation, the Contractor(s) shall promptly carry out the mitigation measures.  DSD will approve the proposed mitigation measures and the ET and IEC shall check that the measures have been carried out by the Contractor(s).

10.4                                  Log-Book

The ET Leader shall keep a contemporaneous log-book of each and every instance or circumstance or change of circumstances which may affect the environmental impact assessment and every non-compliance from the recommendations of the EIA Report or the conditions of the EP.  The ET Leader shall notify the IEC within one working day of the occurrence of any such instance or circumstance or change of circumstance.  The ET Leader’s log-book shall be kept readily available for inspection by persons assisting in supervision of the implementation of the EIA Report recommendations (such as DSD, IEC and Contractor(s)) and the EPs or by EPD or his authorised officers.


11                                        REporting

11.1                                  General

Reports can be provided in an electronic medium upon agreeing the format with DSD and EPD.  The monitoring data (baseline and impact) shall also be made available through a dedicated internet website that shall be agreed with relevant authority.

Types of reports that the ET Leader shall prepare and submit include Baseline Monitoring Report, Monthly EM&A Reports, Quarterly EM&A Summary Reports and Annual EM&A Report and Final EM&A Review Report.  In accordance with Annex 21 of the EIAO-TM, a copy of the monthly, quarterly summary and final review EM&A reports shall be made available to the Director of Environmental Protection.

11.2                                  Baseline Monitoring Report

In respect of the construction phase EM&A works, the ET shall prepare and submit a Baseline Monitoring Report no less than 2 weeks before commencement of the works for the Project for agreement on the A/L Levels.  Copies of the Baseline Monitoring Report shall be submitted to the following: the Contractor(s), the IEC, DSD and the EPD as appropriate.  The ET shall liaise with the relevant parties on the exact number of copies required.  

The Baseline Monitoring Report for the construction phase shall cover the baseline dust and noise levels.  It will include at least the following:

(i)      Up to half a page executive summary.

(ii)     Brief project background information.

(iii)         Drawings showing locations of the baseline monitoring stations.

(iv)         Monitoring results (in both hard and diskette copies) together with the following information:

a.         monitoring methodology;

b.         name of laboratory and types of equipment used and calibration details;

c.         parameters monitored;

d.         monitoring locations (and depth if applicable);

e.         monitoring date, time, frequency and duration; and

f.           QA/QC results and detection limits.

(v)     Details on influencing factors, including:

a.         major activities, if any, being carried out on the site during the period;

b.         weather conditions during the period; and

c.         other factors which might affect the results.

(vi)    Determination of the A/L Levels for each monitoring parameter and statistical analysis of the baseline data, the analysis shall conclude if there is any significant difference between control and impact stations for the parameters monitored;

(vii)    Revisions for inclusion in the Manual; and

(viii)   Comments, recommendations and conclusions.

11.3                                  Monthly EM&A Reports

The results and findings of the construction phase EM&A work required in this Manual will be recorded in the Monthly EM&A Reports prepared by the ET Leader.  The EM&A report shall be prepared and submitted within 2 weeks of the end of each reporting month, with the first report due the month after construction commences.  Each Monthly EM&A Report shall be submitted to the following parties: the Contractor(s), the IEC, DSD and the EPD, as well as to other relevant departments as required.  Before submission of the first Monthly EM&A Report, the ET shall liaise with the parties on the exact number of copies and format of the reports in both hard copy and electronic medium.

The ET Leader shall review the number and location of monitoring stations and parameters every six months, or on as needed basis, in order to cater for any changes in the surrounding environment and the nature of works in progress.

11.3.1                            Contents of First Monthly EM&A Report

(i)      1-2 pages executive summary, comprising:

-        breaches of AL levels;

-        complaint Log;

-        notifications of any summons and successful prosecutions;

-        reporting changes; and

-        forecast of impact predictions.

(ii)     Basic project information including a synopsis of the project organisation, programme and management structure, and a drawing of the Project area showing the environmentally sensitive receivers and the locations of monitoring and control stations, programme, management structure and the work undertaken during the month.

(iii)     Environmental Status, comprising:

-         works undertaken during the month with illustrations (such as location of works, daily dredging/filling rates, percentage fines in the fill material used); and

-         drawing showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations.

(iv)    A brief summary of EM&A requirements including:

-       monitoring parameters;

-       environmental quality performance limits (A/L levels);

-       EAPs;

-       environmental mitigation measures, as recommended in the EIA Report; and

-       environmental requirements in contract documents.

(v)     Advice on the implementation of environmental protection, mitigation and pollution control measures as recommended in the EIA Report and summarised in the updated implementation schedule.

(vi)    Monitoring results (in both hard and diskette copies) together with the following information:

-       monitoring methodology;

-       name of laboratory and equipment used and calibration details;

-       parameters monitored;

-       monitoring locations (and depth); and

-       monitoring date, time, frequency, and duration;

(vii)    Graphical plots of trends of monitored parameters for representative monitoring stations annotated against the following:

-       major activities being carried out on site during the period;

-       weather conditions during the period; and

-       any other factors which might affect the monitoring results;

(viii)   Advice on the solid and liquid wastes management.

(ix)    A summary of non-compliance (exceedances) of the environmental quality performance limits (A/L levels).

(x)     A review of the reasons for and the implications of non-compliance including a review of pollution sources and working procedures.

(xi)    A description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to earlier non-compliance.

(xii)    A summary record of complaints received (written or verbal) for each media, including locations and nature of complaints, liaison and consultation undertaken, actions and follow-up procedures taken and summary of complaints.

(xiii)   A summary record of notifications of summons, successful prosecutions for breaches of environmental protection/pollution control legislation and actions to rectify such breaches.

(xiv)  A forecast of the works programme, impact predictions and monitoring schedule for the next one month; and

(xv)   Comments, recommendations and conclusions for the monitoring period.

11.3.2                            Contents of the Subsequent Monthly EM&A Reports

(i)      Title page.

(ii)     Executive summary (1-2 pages), including:

-    breaches of Action and Limit levels;

-    complaint log;

-    notifications of any summons and successful prosecutions;

-    reporting changes; and

-    forecast of impact predictions.

(iii)     Contents page.

(iv)    Environmental status, comprising:

-    drawing showing the Project area, any environmental sensitive receivers and the locations of the monitoring and control stations;

-    summary of non-compliance with the environmental quality performance limits; and

-    summary of complaints.

(v)     Environmental issues and actions, comprising:

-    review issues carried forward and any follow-up procedures related to earlier non-compliance (complaints and deficiencies);

-    description of the actions taken in the event of non-compliance and deficiency reporting;

-    recommendations (should be specific and target the appropriate party for action); and

-    implementation status of the mitigation measures and the corresponding effectiveness of the measures.

(vii)    Appendices, including:

-    A/L levels;

-    graphical plots of trends of monitored parameters at key stations over the past reporting month for representative monitoring stations annotated against the following: major activities being carried out on site during the period; weather conditions during the period; and any other factors which might affect the monitoring results;

-    monitoring schedule for the present and next reporting period;

-    cumulative complaints statistics; and

-    details of complaints, outstanding issues and deficiencies.

11.4                                  Quarterly EM&A Summary Reports

The ET Leader shall submit Quarterly EM&A Summary Reports for the construction phase EM&A works only.  These reports shall contain at least the following information:

 

(i)            Up to half a page executive summary.

 

(ii)          Basic project information including a synopsis of the Project organisation, programme, contacts of key management, compliance with EP condition (status of submission) and a synopsis of work undertaken during the quarter.

 

(iii)    A brief summary of EM&A requirements including:

-       monitoring parameters;

-       environmental quality performance limits (A/L levels); and

-       environmental mitigation measures, as recommended in the EIA Report.

(iv)    Advice on the implementation of environmental protection and pollution control/mitigation measures as recommended in the EIA Report and summarised in the updated Implementation Schedule.

(v)     Drawings showing the Project area, any environmental sensitive receivers and the locations of the monitoring and control stations.

(vi)    Graphical plots of the trends of monitored parameters over the past four months (the last month of the previous quarter and the present quarter) for representative monitoring stations annotated against:

-         the major activities being carried out on site during the period;

-         weather conditions during the period; and

-         any other factors which might affect the monitoring results.

(vii)   Advice on the solid and liquid wastes management.

(viii)   A summary of non-compliance (exceedances) of the environmental quality performance limits (A/L levels).

(ix)    An Impact Prediction Review will be prepared to compare project predictions with actual impacts for the purpose of assessing the accuracy of predictions on the EIA study.  The review will focus on the comparison between the EIA study prediction with the EM&A monitoring results.  If any excessive variation was found, a summary of investigation and follow up procedure taken shall be addressed accordingly. 

 (x)   A brief review of the reasons for and the implications of non-compliance including review of pollution sources and working procedures.

(xi)    A summary description of the actions taken in the event of non-compliance and any follow-up procedures related to earlier non-compliance.

(xii)   A summarised record of complaints received (written or verbal) for each media, liaison and consultation undertaken, actions and follow-up procedures taken.

(xiii)   Comments (eg effectiveness and efficiency of the mitigation measures), recommendations (eg any improvement in the EM&A programme) and conclusions for the quarter.

(xiv)  Proponents' contacts for the public to make enquiries.

11.5                                  Annual/ Final EM&A Review Reports

An Annual EM&A Report shall be prepared by the ET at the end of each construction year during the course of the Project.  A Final EM&A Review Report shall be prepared by the ET at the end of the construction phase.  The Annual/final EM&A Review Reports shall contain at least the following information:

(i)      Executive Summary (1-2 pages).

(ii)     Drawings showing the project area any environmental sensitive receivers and the locations of the monitoring and control stations.

(iii)    Basic project information including a synopsis of the project organization, contacts for key management staff and a synopsis of work undertaken during the course of the Project.

(iv)    A brief summary of EM&A requirements including:

-       environmental mitigation measures as recommended in the EIA Report;

-       environmental impact hypotheses tested;

-       environmental quality performance limits (A/L Levels);

-       monitoring parameters; and

-       EAPs.

(v)     A summary of the implementation status of environmental protection and pollution control/mitigation measures as recommended in the EIA Report and summarised in the updated Implementation Schedule.

(vi)    Graphical plots and the statistical analysis of the trends of monitored parameters over the course of the project including the post-project monitoring for monitoring stations annotated against the following:

-       the major activities being carried out on site during the period;

-       weather conditions during the period; and

-       any other factors which might affect the monitoring results;

(vii)    A summary of non-compliance (exceedances) of the environmental quality performance limits (A/L levels).

(viii)   A review of the reasons for and the implications of non-compliance including review of pollution sources and working procedures as appropriate.

(ix)    A description of the actions taken in the event of non-compliance.

(x)     A summary record of complaints received (written or verbal) for each media, liaison and consultation undertaken, actions and follow-up procedures taken.

(xi)    A summary record of notifications of summonses and successful prosecutions for breaches of the current environmental protection/pollution control legislations, locations and nature of the breaches investigation, follow-up actions taken and results.

(xii)    A comparison of the EM&A data with the EIA predictions with annotations and explanations for any discrepancies, including a review of the validity of EIA predictions and identification of shortcomings in the EIA recommendations.

(xiii)   A review of the monitoring methodology adopted and with the benefit of hindsight, comment on its effectiveness, including cost effectiveness;

(xiv)     A review of the success of the EM&A programme, including a review of the effectiveness and efficiency of the mitigation measures, and recommendations for any improvements in the EM&A programme.

(xv)       A clear cut statement on the environmental acceptability of the project with reference to specific impact hypotheses and a conclusion to state the return to ambient and/or the predicted scenario as the EIA findings.

11.6                                  Data Keeping

The site documents such as the monitoring field records, laboratory analysis records, site inspection forms, etc. are not required to be included in the EM&A Reports for submission.  However, the documents shall be kept by the ET Leader and be ready for inspection upon request. Relevant information shall be clearly and systematically recorded in the documents.  The monitoring data shall also be recorded in magnetic media, and the software copy shall be available upon request.  The documents and data shall be kept for at least one year after the completion of the construction phase EM&A works.

11.7                                  Electronic Reporting of EM&A Information

To enable the public inspection of the Baseline Monitoring Report and Monthly EM&A Reports via the EIAO Internet Website and at the EIAO Register Office, electronic copies of Monthly EM&A Reports shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF, version 4.0 or later), unless otherwise agreed by EPD and shall be submitted at the same time as the hard copies.  For the HTML version, a content page capable of providing hyperlink to each section and sub-section of the EM&A Reports shall be included in the beginning of the document.  Hyperlinks to figures, drawings and tables in the EM&A Reports shall be provided in the main text where the respective references are made.  Graphics in the reports shall be in interlaced GIF format unless otherwise agreed by EPD.  The content of the electronic copies of the Monthly EM&A Reports must be the same as the hard copies.

 

The internet address and the environmental monitoring data shall be made available to the public via the EIAO Internet Website and the EIAO Register Office.

The internet website as described above will enable user friendly public access to the monitoring data and with features capable of:

·           providing access to environmental monitoring data collected since the commencement of works;

·           searching by data;

·           searching by types of monitoring data;

·           hyperlinks to relevant monitoring data after searching; and

·           or otherwise as agreed by EPD.

11.8                                  Interim Notifications of Environmental Quality Limit Exceedances

With reference to EAPs, when the environmental quality limits are exceeded, the ET shall notify the IEC, Contractor(s), DSD and EPD as appropriate within 24 hours of the identification of the exceedance.  The notification shall be followed up with each party on the results of the investigation, proposed action and success of the action taken, with any necessary follow-up proposals.